supervisor





Project Start:
Project Finish:
Sat 5/1/04
Wed 3/1/06


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Document 5
1 dayMon 5/3/04Mon 5/3/04 0%
2
Supervisor: Plann of activities
1 dayMon 5/3/04Mon 5/3/04 0%
3
A. PREPARATION BEFORE THE ACTUAL PRICE COLLECTION START IN OCTOBER 2004 FOR CPI COUNTRIES
100 daysMon 5/3/04Fri 9/17/04 0%
4
Memorandum item: before anything take place a estimated budget should be submitted and authority should be received to spend
20 daysMon 5/3/04Fri 5/28/04 0%
5
Receive communication letter from National Coordinato directed to retailers asking for permission to take pictures of goods and outlets
1 dayTue 8/31/04Tue 8/31/04Supervisor0%
6
Carry out pre-survey activities
15 daysMon 5/31/04Fri 6/18/04Supervisor0%
7
Test and validate list as well as take photos of goods and outlets
40 daysMon 5/31/04Fri 7/23/04Supervisor0%
8
Receive message from National Coordinator to 1. Add personnel to price collection teams; 2. Add items to list or replace items in list or add outlets to list; 3. Take pictures of additional outlets and/or products
1 dayMon 8/30/04Mon 8/30/04Supervisor0%
9
Receive instructions from National Coordinator regarding final list, date to start collection, form of submission, next visit of Regional Consultants
1 dayTue 9/21/04Tue 9/21/04Supervisor0%
10
Receipt appropriate part of ICP manual (in one of official languages) or of its operations supplement from National Coordinator
1 dayMon 6/21/04Mon 6/21/04Supervisor0%
11
Receive plans for price collection from National Coordinator
10 daysMon 9/6/04Fri 9/17/04Supervisor0%
12
Names of outlets to be enumerated, address & location (maps), products to be priced, pricing forms and photo albums
10 daysMon 9/6/04Fri 9/17/04Supervisor0%
13
Pricing teams, define routes and dates
10 daysMon 9/6/04Fri 9/17/04Supervisor0%
14
Documentation containing information on pricing teams, routes defined and dates to National Coordinator
1 dayMon 9/20/04Mon 9/20/04Supervisor0%
15
B. TRAINING BEFORE THE ACTUAL PRICE COLLECTION START IN OCTOBER 2004 FOR CPI COUNTRIES
110 daysMon 5/3/04Fri 10/1/04 0%
16
Memorandum item: need to have recruitment in place as well as office space for price collectors
20 daysMon 5/3/04Fri 5/28/04 0%
17
Attend training with National Coordinator
10 daysFri 7/2/04Thu 7/15/04Supervisor0%
18
Prepare training material for training of price collectors. Translate the appropriate part of ICP manual or of its operations supplement
10 daysMon 7/19/04Fri 7/30/04Supervisor0%
19
Receive comments from National Coordinator to improve training material orbe advised that the Regional Coordinator will send someone from Head Office to assist in developing improved training materials
1 dayTue 8/17/04Tue 8/17/04Supervisor0%
20
Implement changes and improvements to training materials
10 daysWed 8/18/04Tue 8/31/04Supervisor0%
21
Re-send improved/revised training material to National Coordinator
1 dayWed 9/1/04Wed 9/1/04Supervisor0%
22
Receive comments that training material is accepted and that Regional Coordinator and National Coordinator signed-off on training material
1 dayWed 9/15/04Wed 9/15/04Supervisor0%
23
Print training material
1 dayFri 9/17/04Fri 9/17/04Supervisor0%
24
Preparation of training of price collectors
5 daysMon 9/13/04Fri 9/17/04Supervisor0%
25
Start training of Price Collectors
10 daysMon 9/20/04Fri 10/1/04Supervisor0%
26
D. IMPLEMENTATION PHASE
115 daysTue 10/12/04Mon 3/21/05 0%
27
ICP Data Collection (Price collection)
285 daysMon 10/4/04Fri 11/4/05 0%
28
Collect data for CPI and ICP where necessary to produce the "Augmented CPI" data set
65 daysMon 10/4/04Fri 12/31/04Supervisor0%
29
Submit weekly progress reports to National Coordinator to ensure that the rate at which prices are being collected is adequate
1 dayFri 10/8/04Fri 10/8/04Supervisor0%
30
Submit report of anomalies to National Coordinator
1 dayMon 5/3/04Mon 5/3/04Supervisor0%
31
Receive message from National Coordinator that the next quarter of data collection can proceed
1 dayMon 3/21/05Mon 3/21/05Supervisor0%
32
Visit from Regional Consultants
20 daysMon 10/4/04Fri 10/29/04Supervisor0%
33
Receive feedback from National Coordinator that estimates are adopted as official regional results
1 dayWed 3/1/06Wed 3/1/06Supervisor0%

Resources


IDNameGroupMax UnitsPeak Units
1Supervisor 100%500%
2International Statistical Office 100%0%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
5Receive communication letter from National Coordinato directed to retailers asking for permission to take pictures of goods and outlets Supervisor8 hrsTue 8/31/04Tue 8/31/040%
6Carry out pre-survey activitiesSupervisor120 hrsMon 5/31/04Fri 6/18/040%
7Test and validate list as well as take photos of goods and outletsSupervisor320 hrsMon 5/31/04Fri 7/23/040%
8Receive message from National Coordinator to 1. Add personnel to price collection teams; 2. Add items to list or replace items in list or add outlets to list; 3. Take pictures of additional outlets and/or productsSupervisor8 hrsMon 8/30/04Mon 8/30/040%
9Receive instructions from National Coordinator regarding final list, date to start collection, form of submission, next visit of Regional ConsultantsSupervisor8 hrsTue 9/21/04Tue 9/21/040%
10Receipt appropriate part of ICP manual (in one of official languages) or of its operations supplement from National Coordinator Supervisor8 hrsMon 6/21/04Mon 6/21/040%
11Receive plans for price collection from National Coordinator Supervisor80 hrsMon 9/6/04Fri 9/17/040%
12 Names of outlets to be enumerated, address & location (maps), products to be priced, pricing forms and photo albumsSupervisor80 hrsMon 9/6/04Fri 9/17/040%
13 Pricing teams, define routes and datesSupervisor80 hrsMon 9/6/04Fri 9/17/040%
14 Documentation containing information on pricing teams, routes defined and dates to National Coordinator Supervisor8 hrsMon 9/20/04Mon 9/20/040%
17Attend training with National CoordinatorSupervisor80 hrsFri 7/2/04Thu 7/15/040%
18Prepare training material for training of price collectors. Translate the appropriate part of ICP manual or of its operations supplement Supervisor80 hrsMon 7/19/04Fri 7/30/040%
19Receive comments from National Coordinator to improve training material orbe advised that the Regional Coordinator will send someone from Head Office to assist in developing improved training materialsSupervisor8 hrsTue 8/17/04Tue 8/17/040%
20Implement changes and improvements to training materialsSupervisor80 hrsWed 8/18/04Tue 8/31/040%
21Re-send improved/revised training material to National CoordinatorSupervisor8 hrsWed 9/1/04Wed 9/1/040%
22Receive comments that training material is accepted and that Regional Coordinator and National Coordinator signed-off on training materialSupervisor8 hrsWed 9/15/04Wed 9/15/040%
23Print training materialSupervisor8 hrsFri 9/17/04Fri 9/17/040%
24Preparation of training of price collectorsSupervisor40 hrsMon 9/13/04Fri 9/17/040%
25Start training of Price CollectorsSupervisor80 hrsMon 9/20/04Fri 10/1/040%
28Collect data for CPI and ICP where necessary to produce the "Augmented CPI" data set Supervisor520 hrsMon 10/4/04Fri 12/31/040%
29Submit weekly progress reports to National Coordinator to ensure that the rate at which prices are being collected is adequateSupervisor8 hrsFri 10/8/04Fri 10/8/040%
30Submit report of anomalies to National CoordinatorSupervisor8 hrsMon 5/3/04Mon 5/3/040%
31Receive message from National Coordinator that the next quarter of data collection can proceedSupervisor8 hrsMon 3/21/05Mon 3/21/050%
32Visit from Regional ConsultantsSupervisor160 hrsMon 10/4/04Fri 10/29/040%
33Receive feedback from National Coordinator that estimates are adopted as official regional resultsSupervisor8 hrsWed 3/1/06Wed 3/1/060%